WWW.CO-ASPHALT.COM 2021“Best in Colorado” Asphalt Pavement Awards CATEGORY - Surface Treatment Contractor: A-1 Chip Seal Owner: City of Loveland This $715,000 project included placement of chipseals along 89 collector and residential streets within the City of Loveland. Contract time was 21 days, but A-1 Chip Seal completed the work in just eight days City of Loveland 2021 Surface Treatment Program Spring2022| 17 CATEGORY - Rural In-Place Recycling Category Paving Contractor: Cutler Repaving Material Supplied by: Four Corners Materials Owner: CDOT Region 5 This was the first use of the heater repaving process for CDOT Region 5, which consisted of recycling the upper 1.5” followed with a new 1.5” asphalt layer above. This $6.2M paving operation was accomplished in a single pass, within a single lane closure. The project was completed ahead of schedule in 80 of the 160 contract days. SH 145 Dolores / Rico Heater Repaving Project